PRJ-2601↩ from OFF-2026-0001
Novartis CSV remediation
Novartis Pharma AG·Life Sciences·TK·PM: Martina RossiPlanning
Budget monitoring
2 threshold breaches
- Budget burn 83% over 80% threshold
- Utilization 113% over plan (>100%)
Current budget
EUR 252,000
▲ EUR 12,000 vs baseline · 1 revision
Variance
+5.0%
baseline EUR 240,000
Consumedillus
EUR 210,000
83% burn · EUR 42,000 left
Planned mandaysillus
160
across team
Actual mandaysillus
180
of 160 planned
Utilizationillus
113%
target 85%
Budget figures are live from the budget versions. Consumed / mandays / utilization are illustrative seed data until allocation + time-report data lands. Deferred from this slice: the resource-first PMO monitoring board, soft-on-hard authorization, the AI Controlling-Insights Assistant, and the weekly per-region report.