PRJ-2601↩ from OFF-2026-0001

Novartis CSV remediation

Novartis Pharma AG·Life Sciences·TK·PM: Martina RossiPlanning
Close project
Pre-checks — done or waived
!Final reporting completed manual
!All issues closed 3 still open (live)
!Resource feedback recorded not built — manual
Soft-allocation clean-up — remove releases capacity
ResourceRoleWindowAction
MRSCSV Consultant06-01 → 07-31
GMOValidation Lead06-10 → 06-12

Hard-allocation removal (1.23.2) and reporting/archival (1.23.8) wire in when those land. Role-holders are notified on close.