Ctrl K
PRJ-2607↩ from OFF-2026-934321

HAPPY PATH RAIL — TK QUALIFICATION

·CSV·TK·PM: Martina RossiPlanning
Close project
Pre-checks — done or waived
!Final reporting completed manual
All issues closed
!Resource feedback recorded none recorded — derived from recorded feedback
Soft-allocation clean-up — remove releases capacity
No active soft allocations on this project.

On close, active hard allocations are released (1.23.2) and role-holders plus released resources are notified (1.23.5). Reporting/archival (1.23.8) is still to come.

Complete or waive each pre-check to close