Ctrl K
PRJ-2605↩ from OFF-2026-060601
GOLDEN PATH TEST — TK CSV
—·CSV·TK·PM: Martina RossiPlanning
Delivery Team
0No one assigned yet. Use + Add resource to build the delivery team.
has hours = billable assigned no hours dashed = 0 0 0 yellow = inactive
Loading plan…
Soft plan
Month = the big picture · Day = the fine-editing grid aboveScaleDraft0 soft allocations
| Resourceperson & role | Plan statusdraft → submitted → valid · risk | Aug 2026days · % of month | Sep 2026days · % of month | Oct 2026days · % of month | Nov 2026days · % of month | Dec 2026days · % of month | Total effortall months · intensity | Holds untilexpires if not committed |
|---|---|---|---|---|---|---|---|---|
| PLANNED — SOFT (pale blue · submit → validate · can expire — Renew/Release appear once a row has expired) | ||||||||
| No soft allocations on this project yet. | ||||||||
| COMMITTED — HARD 🔒 (navy solid · changed only via Modify — every change = new version) | ||||||||
| Giulia Moretti CSV Consultant 🔒 | hard · v3 | 100% | 100% | 100% | 100% | 100% | 109 days · full-time | n/a |
prospect soft (fill = how full) hard 🔒 expired over capacityMonth cell shows days (with % of the month beneath) · click → Day view above
Hard allocations
locked rows · ✎ modify (dates/% · replace · release) with reason + impact + version (1.17)| Person | Role | Dates | % | Ver | |
|---|---|---|---|---|---|
| Giulia Moretti | CSV Consultant | 2026-08-01 → 2026-12-31 | 100% | v3 |
Availability check — 2026-08-01 … 2026-12-31
Run a re-check to see unavailable resources.
Alerts, never blocks (CEO directive).
🧩 New resource request
Add the roles you need — a row per role. “Create request” makes one request with all of them; you then search candidates per role inside.
Roles needed
Defining roles doesn’t book anyone — you search candidates per role once the request opens.
Loading…
Does the planned team cover the skills this project needs? Gaps below — “Propose fix” suggests a person or a training action.
Skill gaps
Where the planned team falls short of the required profile.
- Under-allocated −0.6 FTECSV Consultant — under-allocated CSV Consultant under-allocated by 0.6 FTE (1 of 1.6)
- Missing skillGAMP 5 needed for the CSV Consultant role, nobody planned has it
- Missing skillIQ/OQ/PQ needed for the CSV Consultant role, nobody planned has it
Improvement proposals
Deliberated changes (Add / Replace / Adjust) a PM or PMO accepts or rejects.
No proposals yet — use “Propose fix” on a gap above, or “Propose improvement” to add one.