Ctrl K
PRJ-2604↩ from OFF-2026-0088
Chiesi computerised system validation
—·Life Sciences·TM·PM: Clara BianchiExecution
Close project
Pre-checks — done or waived
!Final reporting completed — manual
✓All issues closed
!Resource feedback recorded — none recorded — derived from recorded feedback
Soft-allocation clean-up — remove releases capacity
| Resource | Role | Window | Action |
|---|---|---|---|
| JDK | Project Manager | 07-06 → 07-31 |
On close, active hard allocations are released (1.23.2) and role-holders plus released resources are notified (1.23.5). Reporting/archival (1.23.8) is still to come.
Complete or waive each pre-check to close